Debug – RTC

Set the system real-time clock (RTC), the default setting is “automatic synchronization“, which means the time to synchronize the system when recording data.

18
Mar

Toolbar BTSDA — Cycle Layer/ Step Layer/ Record Layer expand and collapse

The Cycle Layer expand and collapse The Step Layer expand and collapse The Record Layer expand and collapse

18
Mar

View Log

The View Log include Device Log and Local Log, The Local Log is to view the operation log of all channels, and the Device Log is to view the operation log of the current channel. You can package the logs and download to local.

18
Mar

Battery grouping

1 Match data range: Set up grouping conditions, one or more conditions can be applied according to requirements. 2 Within group compare: Used to set the deviation value between groups, one or more options can be selected.   3 Set up the number of batteries in a group, simply click “match”. 4 Click the check box in front of each

Read more

18
Mar

Modify channel color codes

Any channel that is in one of these conditions will be displayed in a color corresponding to the color code. The default color codes: Green is charge; Red is discharge; Yellow is rest. The color codes can be modified to display the work step of channels, the light color of the tester (low machine) is the same as the color

Read more

18
Mar

Battery barcode manage system

The battery barcode can be managed in BTS via battery barcode manage system. By entering the barcode which is combined by channel barcode and battery barcode, we can track and locate the unusual battery signal and search historical data. There 2 methods to enter barcode on your computer:keyboard/barcode scanner. 1.Select the channels you want to generate barcode, click “barcode” on

Read more

15
Mar

Charge and discharge efficiency setting——Charge first,discharge later/discharge first,charge later

Principle behind the setting: The battery material is divided into 2 groups called anode and cathode. Anode or positive electrode will be charged first and discharged later. Charge and discharge rate is discharge capacity/charge capacity. Cathode or negative electrode will be discharged first and charged later. Charge and discharge rate is charge capacity/discharge capacity. The default display setting for cycle

Read more

15
Mar

Clear mark

For the channel under “protected, stopped,paused” status, we can use “clear mark”to change them into “finished” status. Select the channel you want to change, right click, simply click”Clear mark”, as a result, it’s status will be finished. If you have more questions, please contact me with: collin@newarebattery.com

14
Mar

Copy test data

User can copy all the data from software based on their requirements. If you have more questions, please contact me with: collin@newarebattery.com

12
Mar

Curves Setting

Click “Five-Pointed Star” to check the current curve type. Click “+”, customize your curves (X axes, Y axes, background color).